1. Installation Of Floor Mounted Transformer
Installation Of Floor mounted transformer |
This includes civil work, space required, surrounding space, ventilation area, foundation, switch gear etc. The transformer may be indoor or out door.
2. For Civil Works
- Ventilation
- Noise level
- Space required for maintenance/movements
- Trenches for cable run
- Distance between transformer unit and walls.
Walls
Foundation
For rolling wheels of transformer the appropriate rails must be provided on foundation Once the final position of transformer is set on the rails, the rolling wheels are locked prevent movements.
Facility for drainage of oil: Soak pits are provided and also drainage facility for big size transformer are provided.
Cabling : Power cables and control cables should never be placed in the same conduit These should be separate. A suitable trench is provided for cables.
Cable boxes : These are to be filled with insulating oil.
Noise reduction : For this non-reflecting resistance pad is used with the transformer Laid on non vibrating surface.
Fire protection : Buckets full with sand, and carbon tetracloride (CCL4) extinguisher kept at suitable place near to the unit.
Bushings: must be supported properly.
Switch gears : Installation of switch gear are made in separate room. Also power cable and control cable should be run in separate conduits.